This is the story of our first big metallic epoxy project.


This was a 9 day project that consisted of the following:

  • Day 1-3 Grind & patch the concrete

  • Day 4 Apply primer

  • Day 5 Apply epoxy mortar membrane

  • Day 7 Apply metallic primer

  • Day 8 Trowel metallic epoxy

  • Day 9 Apply Urethane



Early in the show, we discuss marketing. We always struggle with whether or not we are being too sale-sy and how that effects our business's image.


Here is a link to the new marketing video we created as a first step to refining our image.


Here is a link to the article that Coatings Pro Magazine wrote about the metallic epoxy project. (Page 40)