Interview with Hugh Agro, President & CEO, and John Meyer, VP Engineering & Development of Revival Gold Inc.
Our previous interview: https://www.cruxinvestor.com/posts/revival-gold-tsxvrvg-positioned-for-a-rising-gold-market-in-2025-6478
Recording date: 31st March 2025
Revival Gold recently released results from the Preliminary Economic Assessment (PEA) for its Mercur gold project, showcasing strong economic potential with projected annual gold production of 95,000 to 105,000 ounces over a 10-year mine life. At a gold price of $2,175 per ounce, the project demonstrates a Net Asset Value (NAV) of $294 million and a 27% Internal Rate of Return (IRR) after tax. These figures improve dramatically at current gold prices of $3,000 per ounce, with NAV increasing to $752 million and IRR to 57%.
The project features modest upfront capital costs of $208 million and competitive operating costs with Cash Costs of $1,205 per ounce and All-in Sustaining Costs of $1,363 per ounce. The resource base consists of approximately 1.4 million ounces of gold, with over 50% in the indicated category, an average grade of 0.6 grams per ton, and metallurgical recovery rates averaging 75%.
A significant advantage of the Mercur project is its location on private patented claims just an hour from Salt Lake City, Utah. This allows for permitting through a state process rather than federal, potentially streamlining the timeline to approximately two years. The strategic location provides ready access to equipment, services, and skilled labor without requiring a camp or remote-site logistics.
The company has outlined a two-phase development approach, with the first phase involving drilling to convert inferred resources to measured and indicated categories, along with collecting metallurgical samples. The second phase will focus on completing a Pre-Feasibility Study and advancing permitting. The combined budget for these phases is approximately $8 million, with potential construction beginning within 2-2.5 years.
Technical risks are mitigated by the project's brownfield status, as the site has been previously mined. Environmental factors appear favorable with no perennial streams, deep groundwater, and no threatened or endangered species identified. The heap leach processing method eliminates the need for tailings facilities, reducing environmental footprint.
Revival Gold's overall portfolio now includes both the Mercur project and the Beartrack-Arnett project, representing a combined resource of approximately 6 million ounces of gold. With a current market capitalization of approximately $50 million, the company is trading at just 0.1x NAV and $8 per ounce of gold resource, suggesting significant potential for value appreciation as the projects advance.
View Revival Gold's company profile: https://www.cruxinvestor.com/companies/revival-gold-inc
Sign up for Crux Investor: https://cruxinvestor.com